PAINTING PROJECT UPDATE AS OF September 5, 2018:

Units 109-115 and 117/119 Castillion Terrace will be finished as of 9/5/18.

Pressure washing will begin on units 135/155, 145-151, and 141/143 this Friday 9/7/18.

The following units have been spray painted and will be back rolled this week: 229-235, 221-227, 209-219, -201-207, 181-187 Palo Verde Terrace.

Units 189-195, 173-179, and 165-171 Palo Verde Terrace have been pressure washed and notices will be posted this week for painting to commence next week 9/10-9/14.

PAINTING UPDATE AS OF September 5

Notices and all necessary information will be provided and posted on the individual buildings.

Fence(s) will be included in the project.

REVISED 2018 Painting Schedule